Subsidy guide · Thane district, Maharashtra
Plan an NHB subsidy polyhouse project in Navi Mumbai
By Editorial Team, Kryzen Biotech · Updated 13 November 2026
A subsidy-eligible protected-cultivation project in Navi Mumbai starts with the scheme route, project area and approval sequence—not with erection. For a commercial project above 2,500 m², NHB can be the route; its In-Principle Approval (IPA) must be obtained before work starts. For an individual farmer’s project under the state mission route, MIDH/NHM supports up to 4,000 m² per beneficiary through the Thane district horticulture office.
- NHB route
- Projects above 2,500 m²
- MIDH / NHM route
- Up to 4,000 m² per farmer
- Cost norms here
- General area
- Structure for this climate
- NVPH or fan & pad

First decide whether MIDH or NHB fits your project
Both schemes use assistance of 50% at the applicable cost norms, but their process and purpose differ. MIDH/NHM is the state-mission route for individual farmers, groups and FPOs, with an area limit of up to 4,000 m² per beneficiary. Apply at the Thane district horticulture office and confirm the current state process and norms before committing money.
NHB is intended for commercial projects by farmers, companies, FPOs and entrepreneurs. It applies above 2,500 m², needs a term loan, and the assistance is credit-linked and back-ended: after completion and inspection, it is credited to the loan account rather than paid as an upfront construction amount. The NHB scheme guidelines state a ceiling of ₹56 lakh per project; current limits and admissible norms should be checked before application.
Do not choose NHB merely because the project is large. Choose it when the commercial scale, DPR, bank finance and IPA process are workable for you. If your area is within 4,000 m², discuss MIDH eligibility at the district horticulture office before deciding the route.
- MIDH/NHM: up to 4,000 m² per beneficiary; apply through the Thane district horticulture office.
- NHB: above 2,500 m²; online IPA and bank term loan are required.
- For either route, verify current norms and state procedures before placing an order.
| MIDH / NHM (state mission) | NHB commercial project | |
|---|---|---|
| Who it is for | Individual farmers, groups, FPOs | Commercial projects: farmers, companies, FPOs, entrepreneurs |
| Project size | Up to 4,000 m² per beneficiary | Above 2,500 m² (1,000 m² in the North-East) |
| Assistance | 50% of cost, up to the cost norm | 50% of project cost at admissible norms, credit-linked and back-ended |
| Ceiling | Area limit per beneficiary | ₹56 lakh per project in the NHB scheme guidelines; check the current limit |
| Bank loan | Not always needed | Needed: subsidy is credited to the term loan |
| Apply at | the Thane district horticulture office | NHB online portal (In-Principle Approval) and your bank |
Design around the wet months, not only April heat
The crop calendar and ventilation plan need to recognise both ends of Navi Mumbai weather. April has the strongest sun, 38.4°C afternoon highs and 7.2 kWh/m²/day sunshine. From June through October, rain and humidity become the dominant challenge: July has 834 mm rain, 90% humidity and only 3.3 kWh/m²/day sunshine.
For a naturally ventilated house, retain the approved ventilation layout rather than altering it during erection. For any structure, select the crop with its monsoon disease and humidity management requirements in mind. A project report should explain why the structure and crop are appropriate for these conditions; an inspector will compare the completed structure against the approved design.
- April: 38.4°C high and 7.2 kWh/m²/day sun.
- July: 834 mm rain, 90% humidity and 3.3 kWh/m²/day sun.
- June–October requires serious rain exclusion and air-movement planning.
| Month | Afternoon high | Night low | Humidity | Rain | Sun (kWh/m²/day) | Wind (m/s) |
|---|---|---|---|---|---|---|
| Jan | 31°C | 15.4°C | 51% | 0 mm | 4.9 | 2 |
| Feb | 33.8°C | 17.6°C | 44% | 2 mm | 5.8 | 2.1 |
| Mar | 36.8°C | 20.6°C | 45% | 5 mm | 6.6 | 2.2 |
| Apr | 38.4°C | 23.1°C | 53% | 3 mm | 7.2 | 2.3 |
| May | 37°C | 25.4°C | 60% | 22 mm | 7.2 | 2.9 |
| Jun | 31.5°C | 25.8°C | 80% | 535 mm | 4.8 | 3.7 |
| Jul | 28.4°C | 24.9°C | 90% | 834 mm | 3.3 | 4 |
| Aug | 27.9°C | 24.2°C | 90% | 606 mm | 3.3 | 3.5 |
| Sep | 28.8°C | 23.6°C | 89% | 376 mm | 4.3 | 2.3 |
| Oct | 30.8°C | 21.6°C | 78% | 104 mm | 5.2 | 1.8 |
| Nov | 30.6°C | 18.6°C | 69% | 17 mm | 4.9 | 2 |
| Dec | 30.3°C | 16.3°C | 60% | 5 mm | 4.6 | 2 |
Crops, planting material and the local selling season
For the high-value vegetable category, the NHB planting-material norm is ₹140 per m². The crop group is suited here for coloured capsicum, parthenocarpic cucumber, lettuce and leafy greens. This is a planting-material norm, not a crop recommendation or assured return; use a crop plan that considers your skill, water quality, disease management and buyer arrangement.
Thane district mandi records give useful season signals. Capsicum was reported across seven markets, with an average modal price of ₹3,893 per quintal; the highest month was July at ₹6,111 and the lowest was February at ₹2,614. Cucumber appeared in five markets, averaging ₹2,202 per quintal, with December the highest month at ₹2,732 and February the lowest at ₹1,686. These are historical mandi observations, not prices that a project can assume.
Other crop groups in the norm table include orchid and anthurium at ₹700 per m², carnation and gerbera at ₹610 per m², and rose and lilium at ₹426 per m². The table identifies gerbera and rose as suited to Navi Mumbai, while orchid and anthurium are marked less suited. Build the DPR around the correct category; do not use a vegetable planting-material norm for a flower project.
- High-value vegetables: ₹140 per m² planting-material norm.
- Capsicum: July was the highest recorded month; cucumber: December was the highest recorded month.
- Use district market records as planning context, not a revenue promise.
| Crop group | NHB norm | Suits Navi Mumbai? |
|---|---|---|
| High-value vegetables | ₹140 per m² | Yes: Coloured capsicum, Cucumber (parthenocarpic), Lettuce and leafy greens |
| Orchid and anthurium | ₹700 per m² | Less suited |
| Carnation and gerbera | ₹610 per m² | Yes: Gerbera and rose |
| Rose and lilium | ₹426 per m² | Yes: Gerbera and rose |
Read the Thane market record before fixing harvest windows
The district market list includes APMC Kalyan, Kalyan, Murbad, Shahapur and their APMC listings. Besides capsicum and cucumber, the records show seasonal differences in protected-cultivation-relevant vegetables. Green peas had the highest reported month in November at ₹12,125 per quintal; beans peaked in July at ₹6,932; green chilli reached ₹5,774 in July; and okra reached ₹4,479 in December.
A peak month alone should not determine what is planted. In Navi Mumbai, the month when a mandi price is high may coincide with difficult monsoon growing conditions. Use the figures to discuss harvest timing and buyer options, then set a realistic crop plan based on the chosen structure.
- Green peas: highest recorded month November.
- Okra and cucumber: highest recorded month December.
- Beans, capsicum and green chilli: highest recorded month July.
| Crop | Markets | Average modal price | Highest month | Lowest month |
|---|---|---|---|---|
| Okra (bhindi) | 8 | ₹3,376/q | Dec (₹4,479) | May (₹2,446) |
| Green peas | 3 | ₹9,410/q | Nov (₹12,125) | Mar (₹6,785) |
| Beans | 6 | ₹4,475/q | Jul (₹6,932) | Jan (₹2,290) |
| Bitter gourd | 8 | ₹3,310/q | Jun (₹4,667) | Oct (₹2,336) |
| Cucumber | 5 | ₹2,202/q | Dec (₹2,732) | Feb (₹1,686) |
| Ridge gourd | 5 | ₹3,636/q | Jul (₹5,548) | Oct (₹2,513) |
| Capsicum | 7 | ₹3,893/q | Jul (₹6,111) | Feb (₹2,614) |
| Green chilli | 4 | ₹4,056/q | Jul (₹5,774) | Sep (₹2,734) |
| Brinjal | 7 | ₹2,949/q | Jul (₹4,493) | Feb (₹2,087) |
| Bottle gourd | 6 | ₹1,689/q | Jul (₹2,732) | Apr (₹1,276) |
Worked one-acre NHB example: what the norm means
The worked example below is a general, non-hilly one-acre illustration for a 3,952 m² fan and pad polyhouse. At the structure cost norm of ₹1,400 per m², eligible structure cost is ₹55,32,800. For high-value vegetables, planting material at ₹140 per m² adds ₹5,53,280, producing an eligible project cost of ₹60,86,080.
At 50% of the norm, the example’s maximum subsidy is ₹30,43,040 (₹30.43 lakh). The shown material price is ₹32,48,775 including GST, or ₹822/m², and is ex-factory without freight or erection. It is a weekly material price, not the eligible project cost and not a sanctioned subsidy figure. The final sanctioned amount depends on the approved project, current norms and inspection.
Navi Mumbai is not under hilly norms in this project information, so do not use hilly figures in the DPR or estimate. For NHB, remember that subsidy is back-ended to the term loan after project completion, rather than available to fund the initial build.
- Example area: 3,952 m², about one acre.
- Example structure: fan and pad polyhouse.
- Indicative only: approval, current norms and inspection determine sanction.
| Item | Amount |
|---|---|
| Structure | Fan and pad polyhouse |
| Area | 3,952 m² (about one acre) |
| Structure cost norm | ₹1,400 per m² |
| Eligible structure cost | ₹55,32,800 |
| Planting material norm (high-value vegetables) | ₹140 per m² → ₹5,53,280 |
| Eligible project cost | ₹60,86,080 |
| Maximum subsidy at 50% of the norm | ₹30,43,040 (₹30.43 lakh) |
| Our material price this week (incl. GST) | ₹32,48,775 (₹822/m²) |
Application order: IPA must come before construction
For MIDH, take the land and project details to the Thane district horticulture office and apply under the state process before beginning work. For NHB, prepare a detailed project report with costs, crop plan and cash flow, file for In-Principle Approval on the NHB portal, and obtain term-loan sanction. NHB has required IPA before work starts since 2017.
Only construct after the relevant approval. Build to the approved design and preserve all quotations, invoices and test certificates. After completion, joint inspection is followed by release to the bank for NHB, while MIDH release follows the state process.
Polyhouse Constructions is a manufacturer of complete material kits from the Satara factory, not an office in Navi Mumbai. Kryzen Biotech’s construction team undertakes erection. The kit can include the GI structure, polyfilm, nets and fittings; the online kit builder shows every item, quantity and that week’s rate.
- NHB sequence: DPR and quotation → IPA → bank term loan → construction → inspection.
- MIDH sequence: apply through the district horticulture route before construction.
- Never start foundations or erection before the applicable approval.
- 1
Pick the structure and size
Match it to Navi Mumbai's climate (see above) and your market. Keep under 4,000 m² for MIDH, or above 2,500 m² for an NHB project.
- 2
Get a quotation and project report
An itemised supplier quotation with HSN codes, and for NHB a detailed project report (DPR) with costs, crop plan and cash flow.
- 3
Apply before you build
MIDH: apply at the Thane district horticulture office. NHB: file for In-Principle Approval on the NHB portal; NHB has required IPA before work starts since 2017.
- 4
Bank loan (NHB)
Get the term loan sanctioned. The subsidy is back-ended: it is paid into the loan account after the project is complete.
- 5
Build to standard
Build with BIS-standard material and keep every test certificate and invoice: inspectors check the structure against the approved design.
- 6
Inspection and release
After a joint inspection, the subsidy is released to your bank (NHB) or to you (MIDH, as per the state process).

Documents and mistakes that can put approval at risk
Keep land records in your name—7/12 extract (Satbara) and 8A in Maharashtra—or a registered lease, along with a site map. Also keep Aadhaar, PAN, bank details, soil and water test reports, and an itemised supplier quotation carrying HSN codes and specifications. Companies and FPOs need their registration papers; NHB applications also need the DPR and bank sanction letter.
The most common error is starting the site work before IPA or before the MIDH application route permits it. Other avoidable errors are a quotation that does not match the sanctioned specification, missing invoices or test certificates, mixing flower and vegetable planting-material categories, and assuming a weekly material rate is a subsidy entitlement.
Our material is manufactured in-house, with a 32-point QA process, lab test certificates with dispatch and a technical data sheet for every product. GI pipes are ISI-marked branded steel from Tata, Jindal and JSW. Keep the supplied paperwork safely for inspection.
- Match the final structure and bills to the approved design.
- Keep material invoices, test certificates and specifications until inspection is complete.
- Use the right crop category and norm in the DPR.
- Land records in your name (in Maharashtra: 7/12 extract (Satbara) and 8A), or a registered lease, with a site map
- Aadhaar, PAN and bank details; for companies and FPOs, registration papers
- Soil and water test report
- Supplier quotation with HSN codes and specifications
- Detailed project report and bank sanction letter (NHB)
- Test certificates and invoices for the material, after purchase

Itemised quotation
Every item with size, quantity, HSN code and GST, ready to attach to the application.

Lab test certificates
Tensile, chemical, salt spray and other tests on the steel, by third-party labs.

ISI-marked GI
GI pipes from Tata, Jindal or JSW steel, with a 15-year warranty.
Buy from India's biggest CEA manufacturing company
Choose your structure and size and get the complete material list, priced this week.
FAQs
Can I apply for NHB subsidy for a 3,952 m² polyhouse in Navi Mumbai?
Yes, 3,952 m² is above the NHB threshold of 2,500 m² for a commercial project. You need NHB In-Principle Approval before work begins and a bank term loan because the subsidy is credit-linked and back-ended.
Should I use MIDH or NHB for a project below 4,000 m²?
MIDH/NHM supports up to 4,000 m² per beneficiary and is applied for through the Thane district horticulture office. NHB is also relevant above 2,500 m² for commercial, loan-funded projects; confirm the suitable route and current norms before applying.
What polyhouse is most practical for Navi Mumbai monsoon conditions?
A naturally ventilated polyhouse is the usual first choice because its film roof keeps the June–October rain off the crop while vents and curtains move air. Fan and pad is a good fit where active cooling is needed, including April conditions.
What documents should I arrange before submitting the project?
Arrange 7/12 extract and 8A or a registered lease, site map, Aadhaar, PAN, bank details, soil and water tests, and an itemised quotation with HSN codes. For NHB, add the DPR and bank sanction letter; retain invoices and material test certificates after purchase.
Is the ₹30.43 lakh figure guaranteed for one acre?
No. ₹30,43,040 is the maximum 50% norm-based subsidy in the indicative 3,952 m² fan and pad example with high-value vegetable planting material. The sanctioned amount depends on the approved project, current norms and inspection.
Subsidy projects near Navi Mumbai
The same guide for nearby towns, with the structure that suits each.
| Town | From Navi Mumbai | District | Cost norms | Suits |
|---|---|---|---|---|
| Subsidy project in Panvel | ~10 km | Raigad | General | NVPH or fan & pad |
| Subsidy project in Mumbai | ~20 km | Mumbai City | General | NVPH or fan & pad |
| Subsidy project in Thane | ~20 km | Thane | General | NVPH or fan & pad |
| Subsidy project in Ambernath | ~30 km | Thane | General | NVPH or fan & pad |
| Subsidy project in Kalyan-Dombivli | ~30 km | Thane | General | NVPH or fan & pad |
| Subsidy project in Ulhasnagar | ~30 km | Thane | General | NVPH or fan & pad |
Sources
- NHB cost norms for protected cultivation
- NHB scheme guidelines (commercial horticulture)
- Mission for Integrated Development of Horticulture
- Kryzen: Polyhouse construction in Navi Mumbai
- Kryzen: Polyhouse farming in Navi Mumbai
- NASA POWER monthly climate averages for Navi Mumbai
- Agmarknet daily prices (data.gov.in)