NHB Subsidy Eligible Protected Cultivation Project in Rayagada
By Editorial Team, Kryzen Biotech · Updated 12 November 2026
Polyhouses and nethouses in Rayagada can get 50% government assistance, but which scheme applies depends on the size of your project, and the amount depends on the government cost norm, not your bill. This page walks through both routes for a project in Rayagada (Rayagada district), with a worked example for the structure that suits Rayagada's climate.
- NHB route
- Projects above 2,500 m²
- MIDH / NHM route
- Up to 4,000 m² per farmer
- Cost norms here
- General area
- Structure for this climate
- NVPH or fan & pad

NHB or MIDH: which scheme fits a project in Rayagada
For a project in Rayagada the first question is size. Up to 4,000 m², the MIDH route through the Odisha horticulture department is usually simpler. Above 2,500 m², an NHB project with a bank loan becomes possible.
| MIDH / NHM (state mission) | NHB commercial project | |
|---|---|---|
| Who it is for | Individual farmers, groups, FPOs | Commercial projects: farmers, companies, FPOs, entrepreneurs |
| Project size | Up to 4,000 m² per beneficiary | Above 2,500 m² (1,000 m² in the North-East) |
| Assistance | 50% of cost, up to the cost norm | 50% of project cost at admissible norms, credit-linked and back-ended |
| Ceiling | Area limit per beneficiary | ₹56 lakh per project in the NHB scheme guidelines; check the current limit |
| Bank loan | Not always needed | Needed: subsidy is credited to the term loan |
| Apply at | the Rayagada district horticulture office | NHB online portal (In-Principle Approval) and your bank |
Worked example: a 3,952 m² project in Rayagada
Take a fan and pad polyhouse of 3,952 m² in Rayagada, growing high-value vegetables. At that size it can go to NHB as a commercial project, or to MIDH since it is under 4,000 m². The most it can receive at NHB's general norms:
| Item | Amount |
|---|---|
| Structure | Fan and pad polyhouse |
| Area | 3,952 m² (about one acre) |
| Structure cost norm | ₹1,400 per m² |
| Eligible structure cost | ₹55,32,800 |
| Planting material norm (high-value vegetables) | ₹140 per m² → ₹5,53,280 |
| Eligible project cost | ₹60,86,080 |
| Maximum subsidy at 50% of the norm | ₹30,43,040 (₹30.43 lakh) |
| Our material price this week (incl. GST) | ₹32,48,775 (₹822/m²) |
Assistance is usually 50% of your actual eligible cost or of the cost norm, whichever is lower, so put every eligible cost in the project report: material, freight, erection, drip and planting material. Our material alone comes to ₹822 per m² this week against a structure norm of ₹1,400; freight and erection come on top.
Mandi price seasons around Rayagada
Prices at the mandis in Rayagada district follow a clear yearly pattern. Tomato is the extreme case, from ₹1,549 per quintal in April up to ₹5,081 in December (228% more). That gap is what protected cultivation lets you aim for: a crop timed to the expensive months.
| Crop | Markets | Average | Highest month | Lowest month | Swing |
|---|---|---|---|---|---|
| Brinjal | 6 | ₹3,648/q | Oct · ₹4,741 | Apr · ₹2,343 | 102% |
| Cabbage | 6 | ₹3,233/q | Oct · ₹4,169 | Apr · ₹2,334 | 79% |
| Tomato | 6 | ₹3,104/q | Dec · ₹5,081 | Apr · ₹1,549 | 228% |
| Cauliflower | 6 | ₹4,164/q | Sep · ₹5,700 | Apr · ₹2,887 | 97% |
| Green chilli | 2 | ₹5,182/q | Aug · ₹6,310 | Dec · ₹4,271 | 48% |
| Okra (bhindi) | 6 | ₹4,155/q | Oct · ₹5,652 | Jun · ₹2,600 | 117% |
| Cucumber | 6 | ₹3,234/q | Sep · ₹4,315 | Mar · ₹2,000 | 116% |
| Beans | 3 | ₹5,250/q | Aug · ₹8,000 | Apr · ₹3,714 | 115% |
When to plant in Rayagada for the best prices
Working back from the month each crop sells highest locally, with typical days from transplanting to first harvest under cover. For example, brinjal peaks in October; at about 60 days to first harvest, transplant in August.
| Crop | Sells best | Days to first harvest | Transplant / sow in | Avoid harvesting in |
|---|---|---|---|---|
| Brinjal | Jul, Aug, Oct | ~60 | August | Apr |
| Cabbage | Aug, Sep, Oct | ~75 | July | Apr |
| Tomato | Nov, Dec | ~75 | September | Apr |
| Cauliflower | Aug, Sep, Oct | ~75 | June | Apr |
| Green chilli | Jul, Aug | ~75 | May | Dec |
| Okra (bhindi) | Oct | ~45 | August | Jun |
| Cucumber | Jun, Jul, Aug, Sep, Oct | ~40 | July | Mar |
| Beans | Jul, Aug | ~50 | June | Apr |
Twelve months of weather in Rayagada
April is the hottest month, with afternoons around 37.6°C; January nights drop to about 11.7°C. July is the wettest (316 mm of 1,449 mm a year), and humidity stays at 75% or more for 5 months. The mildest growing months, with afternoons of 20–32°C and little rain, are Jan, Feb, Nov, Dec.
| Month | Afternoon high | Night low | Humidity | Rain | Sun (kWh/m²/day) | Wind (m/s) |
|---|---|---|---|---|---|---|
| Jan | 25.5°C | 11.7°C | 60% | 8 mm | 4.6 | 1.3 |
| Feb | 30°C | 14.5°C | 51% | 11 mm | 5.4 | 1.5 |
| Mar | 34.7°C | 18.9°C | 44% | 20 mm | 5.8 | 1.7 |
| Apr | 37.6°C | 22.5°C | 43% | 42 mm | 6.3 | 2.1 |
| May | 37.3°C | 24.1°C | 49% | 71 mm | 6.3 | 2.4 |
| Jun | 31°C | 23°C | 73% | 200 mm | 4.6 | 2.9 |
| Jul | 27.5°C | 21.6°C | 87% | 316 mm | 3.6 | 3.1 |
| Aug | 26.9°C | 21.4°C | 89% | 316 mm | 3.7 | 2.7 |
| Sep | 26.9°C | 21°C | 90% | 255 mm | 4.3 | 1.9 |
| Oct | 26.2°C | 18.7°C | 85% | 155 mm | 4.7 | 1.5 |
| Nov | 24.4°C | 14.6°C | 81% | 41 mm | 4.5 | 1.4 |
| Dec | 23.4°C | 11.8°C | 72% | 14 mm | 4.2 | 1.2 |
Steps to apply
- 1
Pick the structure and size
Match it to Rayagada's climate (see above) and your market. Keep under 4,000 m² for MIDH, or above 2,500 m² for an NHB project.
- 2
Get a quotation and project report
An itemised supplier quotation with HSN codes, and for NHB a detailed project report (DPR) with costs, crop plan and cash flow.
- 3
Apply before you build
MIDH: apply at the Rayagada district horticulture office. NHB: file for In-Principle Approval on the NHB portal; NHB has required IPA before work starts since 2017.
- 4
Bank loan (NHB)
Get the term loan sanctioned. The subsidy is back-ended: it is paid into the loan account after the project is complete.
- 5
Build to standard
Build with BIS-standard material and keep every test certificate and invoice: inspectors check the structure against the approved design.
- 6
Inspection and release
After a joint inspection, the subsidy is released to your bank (NHB) or to you (MIDH, as per the state process).

Eligible structures and how they suit Rayagada
All four structures we supply are covered by the schemes. What matters for the project's success is the fit with Rayagada's weather.

Naturally ventilated polyhouse
Best fitFilm roof keeps July–November rain off the crop; roof vents and roll-up curtains move air without power. The usual first choice in Rayagada.

Fan & pad polyhouse
Good fitExhaust fans pull air through wet pads. In April that can take a 40°C afternoon down to about 32°C inside, cool enough for leafy greens.

Square nethouse
SeasonalFlat-roof 4 × 4 m grid with shade and insect net, the NHB nursery design. Best from November to February, when rain is low.

Curved nethouse
SeasonalArched GI frame covered in shade net: taller crops, more air and a lower cost than a polyhouse. Rain passes through, so pick crops that tolerate it.
Planting material norms and crops that suit
NHB also counts planting material and cultivation in the project cost, at these norms. The right column shows which groups suit this climate.
| Crop group | NHB norm | Suits Rayagada? |
|---|---|---|
| High-value vegetables | ₹140 per m² | Yes: Coloured capsicum, Cucumber (parthenocarpic), Lettuce and leafy greens |
| Orchid and anthurium | ₹700 per m² | Less suited |
| Carnation and gerbera | ₹610 per m² | Yes: Gerbera and rose |
| Rose and lilium | ₹426 per m² | Yes: Gerbera and rose |
Documents you will usually need
- Land records in your name (in Odisha: ROR (Khatian)), or a registered lease, with a site map
- Aadhaar, PAN and bank details; for companies and FPOs, registration papers
- Soil and water test report
- Supplier quotation with HSN codes and specifications
- Detailed project report and bank sanction letter (NHB)
- Test certificates and invoices for the material, after purchase
What we provide for your file:

Itemised quotation
Every item with size, quantity, HSN code and GST, ready to attach to the application.

Lab test certificates
Tensile, chemical, salt spray and other tests on the steel, by third-party labs.

ISI-marked GI
GI pipes from Tata, Jindal or JSW steel, with a 15-year warranty.
Material for your Rayagada project
We supply the complete material for subsidy projects in Odisha from our Satara factory, about 1,310 km from Rayagada. See the kit and live price for your structure:
Rayagada within Odisha
Among the 33 towns we supply in Odisha, Rayagada ranks 20th for summer heat and 22nd for yearly rain. Other Odisha towns on our list:
- Subsidy project in Nabarangapur
- Subsidy project in Bhubaneswar
- Subsidy project in Cuttack
- Subsidy project in Brahmapur
- Subsidy project in Rourkela
- Subsidy project in Puri
- Subsidy project in Sambalpur
- Subsidy project in Baleshwar Town
- Subsidy project in Bhadrak
- Subsidy project in Baripada Town
- Subsidy project in Balangir
- Subsidy project in Jharsuguda
Buy from India's biggest CEA manufacturing company
Choose your structure and size and get the complete material list, priced this week.
FAQs
Is a polyhouse in Rayagada eligible for NHB subsidy?
Yes, if the project is above 2,500 m² and set up as a commercial project with a bank loan. NHB gives a credit-linked, back-ended subsidy of 50% of project cost at its norms. Smaller projects can apply under MIDH through the Rayagada district horticulture office.
How much subsidy can I get on 1 acre in Rayagada?
For a 3,952 m² fan and pad polyhouse with high-value vegetables, up to about ₹30.43 lakh at NHB's general norms (50% of ₹60,86,080). The sanctioned figure depends on the approved project.
Do you help with the subsidy file?
We provide the itemised quotation, specifications and test certificates the file needs. The application itself is made by you to the department or NHB.
Is the subsidy paid on my bill or on the cost norm?
Usually on whichever is lower: your actual eligible cost or the admissible cost norm. Include every eligible cost (material, freight, erection, irrigation, planting material) in the project report.
Can I build first and apply later?
No. NHB requires In-Principle Approval before work starts, and MIDH applications are approved before the structure is built. Apply first.
Are hilly-area norms used in Odisha?
Not generally; Odisha uses general-area norms.
Subsidy projects near Rayagada
The same guide for nearby towns, with the structure that suits each.
| Town | From Rayagada | District | Cost norms | Suits |
|---|---|---|---|---|
| Subsidy project in Parvathipuram | ~60 km | Vizianagaram | General | NVPH or fan & pad |
| Subsidy project in Bobbili | ~90 km | Vizianagaram | General | NVPH or fan & pad |
| Subsidy project in Salur | ~100 km | Vizianagaram | General | NVPH or fan & pad |
| Subsidy project in Sunabeda | ~100 km | Koraput | General | NVPH or fan & pad |
| Subsidy project in Rajam | ~110 km | Srikakulam | General | NVPH / nethouse |
| Subsidy project in Bhawanipatna | ~110 km | Kalahandi | General | NVPH or fan & pad |