Polyhouse Electrical Load Calculation: Connected Load, Cable Size and Power Cost
Polyhouse Constructions Agronomy Desk · 13 નવે, 2026
A correct polyhouse electrical load calculation prevents two expensive problems: a sanctioned connection that is too small for summer operation, and oversized electrical work that adds unnecessary capital cost. Start with the nameplate input of every fan, pump, actuator, light and controller. Add all installed equipment for connected load, then identify what can run at the same time to estimate maximum demand and electricity use.
For a naturally ventilated polyhouse, irrigation pumps and a few small motors often dominate. A fan-and-pad polyhouse needs a much more careful three-phase design because exhaust fans, cooling-pad pumps, foggers and circulation fans may run together during hot afternoons.
Important: Use the equipment nameplate kW or input current, not only the motor HP mentioned in a quotation. Final cable size, MCB/MCCB rating, earthing and panel design must be checked by a licensed electrical engineer or electrician under local supply rules.
Start by separating the four numbers
These terms are often mixed up when farmers apply for an electricity connection. They mean different things.
Electrical term | What it means | Why it matters in a polyhouse |
|---|---|---|
Connected load | Total rated kW of every installed item | Used as the full inventory of appliances and often required in paperwork |
Running load | kW being consumed at one particular time | Changes between irrigation, cooling and idle periods |
Maximum demand | Highest realistic running load when required equipment operate together | Helps choose sanctioned load, transformer capacity and incomer rating |
Energy consumption | Running load × operating hours, measured in kWh or units | Determines the electricity bill |
For example, a structure may have 18 kW of equipment installed. But if the irrigation pump never runs with the cooling system, the maximum demand may be only 13–15 kW. Do not assume all equipment will be off during irrigation, however. In a hot month, cooling equipment cannot be stopped just because fertigation is running.
A sensible preliminary rule is to retain a 10–25% future margin above calculated maximum demand. The right margin depends on plans for another borewell pump, packhouse refrigeration, lighting, automation or expansion. Ask the distribution company and your electrician whether the requested sanctioned load is in kW or kVA and whether a three-phase connection is required.
Make an equipment schedule before doing any maths
Walk through the farm and list permanent loads, including equipment outside the polyhouse that shares the same connection. This can include the source pump, filtration pump, fertigation unit, office load, security lights, packhouse fans and cold room if applicable.
Create separate rows for equipment that looks similar but has different ratings. For instance, two exhaust fans may have one motor rating while HAF (horizontal airflow) fans have another. Cooling-pad circulation pumps and fogger pumps must also be listed separately.
Information to copy from each nameplate
Record these details in a register or spreadsheet:
- Equipment name and quantity.
- Rated input in kW, or rated voltage and amperes.
- Supply type: 230 V single phase or 415 V three phase.
- Whether it is a motor load, heater, lighting or electronic controller.
- Expected operating hours in each season.
- Whether it runs at the same time as other equipment.
- Distance from the main panel to the load, in metres.
If a motor nameplate only gives HP, obtain its rated input current or input kW from the supplier. HP describes output at the shaft; electricity drawn at the meter is higher because motors have efficiency and power-factor losses. Never treat 1 HP as exactly 0.746 kW of electrical consumption.
For fan-and-pad houses, first ensure that fan quantity is based on the ventilation design. See this guide on calculating exhaust fan size for a fan-and-pad polyhouse. An incorrect fan count makes both cooling performance and the electrical estimate wrong.
Calculate connected load and maximum demand
The basic connected-load equation is simple:
Connected load (kW) = sum of quantity × rated input kW for every item
Then create a summer peak operating scenario. In most Indian plains, this is usually a hot afternoon when ventilation and cooling are working at their highest level. Add only the equipment that can genuinely be ON together.
Example: illustrative 1,000 m² fan-and-pad polyhouse
This is an example only, not a standard equipment schedule. Fan count, motor size and pump size vary with house dimensions, ventilation target, pad arrangement, water head and climate.
Load | Quantity × assumed input | Connected load (kW) | Runs in hot-afternoon peak? | Peak running load (kW) |
|---|---|---|---|---|
Exhaust fans | 6 × 0.75 kW | 4.50 | Yes | 4.50 |
HAF fans | 6 × 0.18 kW | 1.08 | Yes | 1.08 |
Cooling-pad circulation pump | 1 × 1.50 kW | 1.50 | Yes | 1.50 |
Fogger pump | 1 × 1.10 kW | 1.10 | Sometimes | 1.10 |
Fertigation/irrigation pump | 1 × 2.20 kW | 2.20 | Yes, if irrigation overlaps | 2.20 |
Dosing unit, filters and controls | 1 × 0.50 kW | 0.50 | Yes | 0.50 |
Lighting, sensors and small loads | — | 0.40 | Yes | 0.40 |
Total |
| 11.28 kW |
| 11.28 kW |
In this illustration, connected load and peak load happen to be the same because all listed equipment could run together. If fogging is interlocked to stop when the pad system runs, or irrigation is scheduled at night, the actual maximum demand can be lower. That operating logic must be written down, not assumed.
For the connection request, an initial planning allowance might be around 12.5–14 kW, after allowing modest spare capacity. The final sanctioned load must follow the local electricity distribution company’s rules. A three-phase service will normally be appropriate once several motors are involved, and it helps distribute load more evenly.
For a naturally ventilated house, the schedule may be much smaller: irrigation and fertigation pumps, a roll-up curtain motor if fitted, small foggers, lighting and controls. Learn the operational difference in NVPH versus fan-and-pad polyhouse; the choice changes recurring power cost as much as it changes initial equipment needs.
Convert kW into current for panels and cables
Cable and switchgear are selected primarily by current, not just by total kW. The most useful formulas for preliminary calculation are below.
For a single-phase load:
Current (A) = kW × 1,000 ÷ (230 × power factor)
For a three-phase load:
Current (A) = kW × 1,000 ÷ (1.732 × 415 × power factor)
Motors commonly have a power factor below 1. For a preliminary mixed-motor estimate, an assumed power factor of 0.8–0.9 may be used where actual values are unavailable. Use the nameplate current for the final design.
In the illustrative 11.28 kW three-phase example, using a power factor of 0.85:
Current = 11,280 ÷ (1.732 × 415 × 0.85) = about 18.5 A
This is the expected running current at that assumed load. It does not mean that a cable rated exactly 18.5 A is safe or suitable. Cable choice also depends on installation method, ambient temperature, grouping with other cables, route length, permissible voltage drop, motor-starting current and future capacity.
Cable planning: what your electrician needs
Give your electrician the equipment schedule and a simple site drawing. Ask for a cable calculation that checks all of the following:
- Main incomer current and expected maximum demand.
- Each outgoing circuit separately: exhaust fan bank, HAF fans, pad pump, fogger pump, irrigation pump and controls.
- Copper or aluminium conductor, number of cores, armouring and insulation grade appropriate for the route.
- Cable ampacity after derating for heat, conduit, tray, direct burial and grouping.
- Voltage drop from meter/panel to the farthest motor.
- Motor starter type and starting current.
- Earthing conductor size, earth pits and bonding of metal equipment.
- MCB/MCCB, overload relay, contactor, isolator and surge protection ratings.
A long cable run is important in farms. A motor may start weakly or overheat if voltage at the far end falls too low, even when the cable seems adequate by ampacity. Keep the main panel reasonably close to the load centre where possible, then use properly protected sub-panels for distant areas.
Do not feed multiple motors from one unprotected branch cable. Each motor needs suitable isolation and overload protection. Motors also draw several times their normal current during starting. Direct-on-line starting, star-delta starting and variable-frequency drives have different implications for the supply and protection settings.
Estimate monthly electricity consumption and operating cost
Electricity consumption is measured in units, where:
1 unit = 1 kWh
For each load:
Monthly units = input kW × average running hours per day × number of days
Then:
Estimated energy charge = monthly units × your applicable ₹/unit tariff
Your bill may also contain fixed charges, demand charges, taxes and other charges. Therefore, use the tariff sheet for your connection category rather than multiplying all units by one assumed rate.
Sample hot-month energy budget
Using the same illustrative equipment, assume this operating pattern for 30 days:
Equipment group | Average combined input | Average hours/day | Estimated monthly use |
|---|---|---|---|
Exhaust fans | 4.50 kW | 7 hours | 945 kWh |
HAF fans | 1.08 kW | 12 hours | 389 kWh |
Pad pump | 1.50 kW | 5 hours | 225 kWh |
Fogger pump | 1.10 kW | 2 hours | 66 kWh |
Irrigation/fertigation | 2.70 kW | 2 hours | 162 kWh |
Controls and lights | 0.40 kW | 12 hours | 144 kWh |
Estimated monthly total |
|
| 1,931 kWh (units) |
This is only a planning example. In a cloudy monsoon week, fans and pad pumps may run far less. In peak April–May weather, runtime can rise sharply. Crop stage, set points, outside humidity, shading and operator practice all matter. Log daily meter readings and controller run-hours for at least one season; that gives a more useful budget than any generic annual estimate.
It is also wise to model two separate cases: a summer peak-month estimate for cash-flow planning and a year-round average estimate for crop economics. Cooling-pad maintenance has a direct effect on power efficiency. Poor water distribution, algae and scale make the system work harder; follow a planned cellulose cooling-pad maintenance schedule.
Reduce load without risking the crop
The aim is not to keep every motor off. It is to run only the equipment needed to maintain crop conditions.
- Use temperature, humidity and timing controls so fan stages, pumps and foggers do not operate unnecessarily.
- Interlock cooling equipment correctly. For example, a pad pump should operate when its associated exhaust fans require evaporative cooling, not run for long periods without useful airflow.
- Maintain fan shutters, belts, bearings and blades. A struggling fan can draw excess current and deliver less air.
- Clean filters and check pressure regularly in irrigation and fogging systems. Blocked filters increase pumping energy and reduce uniformity.
- Balance three-phase loads across phases. Severe imbalance causes voltage problems and can damage motors.
- Check actual voltage at the panel and farthest motor during peak operation. Repeated low voltage needs attention from an electrician and, where relevant, the supply utility.
- Fit appropriately rated protection and earthing. Saving money by undersizing protection or bypassing overload relays is unsafe and risks motor failure.
For farms considering solar support, size it from the priority load profile, not simply from total connected load. Fans protecting a high-value crop during a power cut may deserve backup priority, while irrigation can sometimes be shifted. Read how to choose solar power for polyhouse fans and pumps before deciding between solar generation, battery backup and a generator.
A practical checklist before you apply for power
Use this checklist with your supplier, electrician and farm manager:
- List every present and planned electrical item with nameplate kW/current.
- Prepare summer, winter and irrigation operating scenarios.
- Calculate connected load and highest simultaneous running load.
- Add a realistic 10–25% expansion margin.
- Confirm whether the connection should be single phase or three phase.
- Calculate feeder current, branch-circuit currents and voltage drop for actual cable lengths.
- Specify independent protection for each motor and an accessible emergency isolator.
- Plan earthing, lightning protection and surge protection for the exposed farm site.
- Keep the electrical panel dry, lockable and away from direct fogger spray or pad splash.
- After commissioning, record actual current, voltage and monthly units; revise the estimate after the first hot season.
Next steps
First prepare the equipment schedule from actual fan, pump and controller nameplates. Then have a qualified electrician convert it into a single-line diagram, cable schedule and protection plan before ordering electrical material or applying for the connection.
If you are still deciding on the structure and cooling system, compare the equipment needs of a fan-and-pad polyhouse with a naturally ventilated design. For structure and covering material quantities, you can build your kit and view this week’s rates; electrical work should be budgeted separately with a local licensed contractor.
Frequently asked questions
How much sanctioned load is needed for a 1-acre polyhouse?
There is no single figure. A naturally ventilated 1-acre house may need far less power than a fan-and-pad house, while borewell pumps, packhouse loads and cooling equipment can raise the requirement significantly. Calculate from actual equipment nameplates and the maximum loads that run together.
Should I calculate load in HP or kW?
Use kW or rated current from the motor nameplate for electrical planning. HP is motor output, while the input power drawn from the supply is affected by motor efficiency and power factor.
Do exhaust fans and cooling-pad pumps run together?
Yes, in normal evaporative cooling operation the exhaust fans pull air through the wetted cooling pads, so both should be included in the peak summer scenario. The exact staging depends on the climate controller settings and crop requirement.
Can I use one cable for all polyhouse motors?
A main feeder can supply a properly designed distribution panel, but individual motor circuits need suitable protection, isolators and cable sizing. Combining all motors on an inadequately protected cable is unsafe and makes faults harder to locate.
How can I find the actual electricity use after installation?
Read the electricity meter at the same time each day or week, and record fan and pump run-hours from the controller. A clamp meter used by a qualified electrician can also verify actual running current and identify unusually loaded motors.